DND DEVELOPERS · NOVEMBER 2026
Royal Golf View: power installations and finishing progress
Explore the November update from Royal Golf View Apartment Hotel in Kacyiru, Kigali, with progress on power installations, interior finishes and external works.
Watch the November highlights
Finishing progress in Blocks A and B
The November newsletter reports blockwork and plastering complete in both blocks. Plumbing, ceilings, screeding, aluminium and tiling are each at 98%; painting and carpentry at 95%; electrical works and plumbing fixtures at 90%; and basement finishing at 75%.
Block C and external works
Block C civil and structural works are reported at 100%, MEP works at 40% and blockwork at 50%. External progress includes landscaping and fencing at 85%, concrete works at 80%, swimming pool works at 75% and external finishing at 45%.
Power systems and pre-handover work
Generator and transformer/main-distribution installation are reported at 100%. The newsletter also describes lighting installation, firefighting and sewage-treatment system testing, interior finishes and pre-handover snagging. These figures and work descriptions reflect the supplied November 2026 newsletter. Project completion is expected in December 2026.
Read and download the full November newsletter
Explore all four pages, including the construction timeline and detailed progress tables.